DoD Waste and Incompetence Cited by IG in sourcing spare parts for M2 Heavy Machine Gun

Posted by:

Thanks to Mother Jones writer Adam Weinstein who brought this item to our attention, SFTT has reviewed a recent DoDIG report  (Department of Defense Inspector General) that documents yet more absolutely blithering incompetence inside the multi-billion dollar DoD Procurement bureaucracy.  The issue in this case is spare parts for the M2 .50-caliber Heavy Machine Gun (“HMG”), better known as “Ma Duece” by those who rely upon it to reach out and “touch” Jihad Johnny in a memorable way.

M-2 Heavy Duty Machine Gun

 

This DoD IG investigation was kicked off by field reports of slow-to-no response for critical spare parts needed to keep their M2’s in “lethal” condition. When DoD IG inspectors looked into cited complaints, they found a level of incompetence that would be laughable were it not for the reality that these M2’s are life-saving to our troops and death-dealing to our enemy when they are fully functioning. But, when M2’s are sidelined for lack of spare parts, we all know who pays the price in blood and gore for not having their HMG to hammer through mudwalls or to nail some jihadii who is out of range of the pathetically under-powered M-4 carbine

Here’s what the DoDIG folks staked out as their objective on this investigation: “What We Did: We determined whether the Defense Logistics Agency (“DLA”) used appropriate and effective contracting procedures to provide customers with critical application M2 machine gun parts.”  Now for the meat of their findings: 

DLA did not have effective internal controls in place to ensure appropriate and effective contracting procedures related to contract quality assurance, product quality deficiency report processing, spare part kit assembly, and oversight of contractor deliveries. Specifically,

  • Contractors provided at least 7,100 non-conforming parts on 24 contracts.
  • DLA did not adequately process 95 of 127 product quality deficiency reports.
  •  DLA did not deliver 60 spare part kits on time to support a U.S. Army program to overhaul 2,600 M2 machine guns and provided non-conforming parts in kits.
  • DLA did not pursue adequate compensation from contractors who were significantly late in providing critical parts on 49 contracts.

As a result,

  • Warfighters had to wait for critical M2 gun parts as DLA had backorders on 7,183 requisitions for 60,701 parts during a 12-month period. Priority group 1 comprised 4,097 of these requisitions for 40,333 parts.
  • A US Army program to overhaul M2 machine guns was negatively impacted.
  • DLA missed opportunities to identify contractors with performance problems and obtain adequate compensation.
  • Because of the quality problems, the Government spent at least $655,000 in funds that could have been put to better use.
  • DLA missed an opportunity to obtain approximately $405,000 in contractor compensation for late deliveries.
  • DLA has initiated several corrective actions to improve the quality of M2 machine gun parts.
  • Implementing our recommendations should improve DLA’s internal controls over contracting.

 Here’s the DoDIG “kicker” for DLA:  “. . . establish controls and implement measures to improve its contract quality assurance procedures, product quality deficiency report processing, spare part kit assembly, and contractor delivery oversight . . .”  This is equivalent to the DoDIG telling the Secretary of Defense that no such effective controls and measures are currently in place. That’s right, in 2010, after over eight years of combat in Afghanistan and seven years of combat in Iraq, the desk-jockeys of DLA do not have a minimally-acceptable process that gets our frontline troops the right spare parts for their M2’s in a timely fashion.

The sad truth is that no one involved demonstrated even a minimal concern about getting critical spare parts to those whose very survival might well depend on getting them in a timely manner, i.e., before their next firefight. 

There is more to this report that I will be covering in a subsequent article.  However, for those who have followed SFTT’s investigation of the mix of unexplainable behavior and incompetence that produced the Interceptor Body Armor fiasco, this report on the shoddy procurement process within the DoD only confirms that the problems indentified by SFTT are truly systemic and not unique to body armor. 

It is absolutely unacceptable that we seem unable or unwilling to provide our men and women serving in harm’s way the proper equipment to do their job and come home alive in one piece.  Folks, we have a serious problem in our military procurement system and unless  Americans raise their voice and say “enough,” it is likely to continue that way.  Find out what you can do to support SFTT’s mission by becoming a Member or by Volunteering your services to get the SFTT message across to our Congressional and military leaders. 

Roger Charles

Senior Investigative Reporter and Editor

1
  Related Posts